Pipe Support Spacing Calculator

Determine support intervals per UPC/IPC requirements

Support Requirements

Maximum Support Spacing --
Number of Supports Required --
Base Support --
Mid-Span Supports --
Recommended Hanger Type --
Support requirements and notes will appear here.

Support at Changes

  • Support within 12" of each fitting
  • Support within 18" of valves
  • Support at each change of direction
  • Support at each floor penetration
  • Support at base of vertical risers
  • Support at top of vertical risers

Hanger Types

Type Application
Clevis HangerHorizontal suspended pipe
J-Hook/WireLight-duty, small pipe
Ring HangerVertical pipe support
Riser ClampVertical riser support
Pipe StrapSurface-mounted pipe
TrapezeMultiple parallel pipes

Horizontal Pipe Support Spacing (UPC/IPC)

Material 1/2" - 1" 1-1/4" - 2" 2-1/2" - 3" 4" - 8"
Copper6 ft10 ft10 ft10 ft
CPVC3 ft4 ft4 ft4 ft
PEX32"32"----
PVC4 ft4 ft4 ft4 ft
ABS4 ft4 ft4 ft4 ft
Cast Iron5 ft5 ft5 ft5 ft
Steel12 ft12 ft12 ft12 ft
Stainless10 ft10 ft10 ft10 ft
Per UPC Table 313.3 / IPC Table 308.5. Check local amendments.

Vertical Pipe Support Spacing

Material All Sizes Notes
Copper10 ft (every floor)Support at base and each floor
CPVC10 ft (every floor)Use riser clamps, allow movement
PEX4 ftMore frequent support needed
PVC4 ftEvery floor minimum
ABS4 ftEvery floor minimum
Cast Iron15 ft (every floor)Support at each hub/joint
Steel15 ft (every floor)Use riser clamps

Special Considerations

Hot Water

  • Allow for thermal expansion
  • Use roller supports for long runs
  • Expansion loops/offsets
  • Guides at direction changes

Plastic Pipe

  • Closer spacing required
  • Continuous support preferred
  • No point loading
  • Wide bearing surface

Insulated Pipe

  • Support outside insulation
  • Insulation shields at hangers
  • Prevent compression
  • Maintain vapor barrier

Seismic

  • Lateral bracing required
  • Flexible connections
  • Per ASCE 7 / local code
  • Max 40 ft spacing